Sewer and stormwater renewal
Recent rehabilitation and ongoing workCity renewal programs maintain sanitary sewers, storm drains and streambanks. Recent work includes pipe and manhole rehabilitation, channel repairs and retirement of an older Grand Avenue sewer segment.
Project images and plans
Projects & phases
- 2025 Sewer Manhole Rehabilitation Program
- Work complete; testing underway · 2026-09-10 · 31 manholesSource
- 2025 Sewer Pipe Rehabilitation Program
- Substantially complete; final restoration · 2026-03-19Source
- 2025 Storm Pipe Rehabilitation Program
- Substantially complete; final restoration · 2026-07-29Source
- 2025 Channel Repair Program
- Substantially complete; final restoration · 2026-09-10 · Five locationsSource
- Grand Avenue Sewer Abandonment — S.33rd to Jordan Creek
- Work ongoing · 2026-09-10Source
- 16th Street / Grand Avenue storm drainage
- Intersection improvements include larger drainage infrastructure; underway in September 2026 with a spring 2027 project target.Source 1Source 2
- Sugar Creek Sponsored Project Improvements — Phase 2
- 3,000 feet of streambank restoration between Mills Civic Parkway and Stagecoach Drive; $2,009,820 construction contract reported in the October 20 packet.Source
- Blue Creek Stormwater Detention Facilities
- Accepted November 17, 2025.Source
- 2023 Channel Repair Program
- Accepted November 17, 2025.Source
- 2024 Sewer Manhole Rehabilitation Program
- Accepted December 1, 2025.Source
Project context
City renewal programs maintain sanitary sewers, storm drains and streambanks. Recent work includes pipe and manhole rehabilitation, channel repairs and retirement of an older Grand Avenue sewer segment.
Documents & sources
Official records and reporting, with access limitations noted.
City construction updatesPrimary public project record→City September 10, 2026 update noticePrimary public project record→16th Street / Grand Avenue scopeMay 18, 2026 council communication→Sugar Creek sponsored restoration progressWRA October 20, 2026 packet · contract progress→November 17, 2025 acceptance minutesBlue Creek detention and 2023 Channel Repair · Vote 25-441→December 1, 2025 acceptance minutes2024 Sewer Manhole Rehabilitation · Vote 25-478→
Open questions
- Follow the linked city records for future phases and completion updates.